Team SHUNYAIIT BOMBAY

2024–25 / Buildings & retrofits / Healthcare retrofit proposal

SEVA

A retrofit proposal for the Community Healthcare Centre in Palghar links patient circulation, ventilation and power.

THE QUESTION

SEVA / DESIGN BRIEF

How can an existing community hospital expand care and improve infection control?

The proposed entrance to the Palghar community health centre. Architectural rendering.SEVA project artwork in the 2025 competition submission.
SEVA / ENGINEERING JOURNAL01 / 02

Follow the patient route

CHAPTER 01

Follow the patient route

Clearer zoning, wayfinding and waiting spaces organise the flow of patients through the building.

The proposed entrance to the Palghar community health centre. Architectural rendering.
CHAPTER 02

Inspect the services

The proposal pairs daylight and passive ventilation with efficient HVAC, smart energy controls and solar generation.

SEVA project artwork in the 2025 competition submission.

WHAT WE LEARNED

What the team learned

The existing facility had 30 beds. The design target of 60 beds required the team to consider access and crowding alongside energy demand.

PROJECT MILESTONE

Result

Presented at the BuildingsNEXT Student Design Showcase on 26 April 2025.

See all SEVA photographs ↗

THE PEOPLE

Team SHUNYA, IIT Bombay. Follow-on heat-pump research was led by Shubhanshu Rai and Althaf Shaik.

Work with the team on the next project ↗

NEXT EXPLORATION

Samsara

↗